Number* | Standard Title | Initial Enforcement Date / Decision | Inactive Date / Decision | Notes |
---|---|---|---|---|
BAL-001-0.1a
|
Real Power Balancing Control Performance | April 1, 2015
D-2014-216 |
April 1, 2017
D-2017-012 |
|
BAL-002-1
|
Disturbance Control Performance |
April 1, 2015
|
April 1, 2021
|
|
BAL-003-1.1
|
Frequency Response and Frequency Bias Setting |
April 1, 2017
|
December 1, 2021
|
|
BAL-004-0
|
Time Error Correction | January 1, 2016
D-2015-168 |
November 5, 2019
D-2019-139 |
|
BAL-005-0.2b
|
Automatic Generation Control | January 1, 2016
D-2015-168 |
January 1, 2017
D-2016-195 |
|
BAL-005-0.2b
|
Automatic Generation Control |
January 1, 2017
|
July 1, 2021
|
|
BAL-006-2
|
Inadvertent Interchange | April 1, 2015
D-2014-216 |
January 1, 2019
D-2018-179 |
In its decision D-2018-179, the Régie suspends the Enforcement of Requirements 1, 2, 4 and 5 as of January 1, 2019. |
BAL-006-2
|
Inadvertent Interchange |
April 1, 2015
|
July 1, 2021
D-2020-067 |
|
CIP-002-5.1
|
Cyber Security - BES cyber System Categorization | January 1, 2017
D-2016-119 D-2016-138 D-2017-031 |
April 1, 2019
|
|
CIP-003-5
|
Cyber Security — Security Management Controls | January 1, 2017
D-2016-119 D-2016-138 D-2017-031 D-2017-069 |
January 1, 2018
D-2017-117 |
|
CIP-003-6
|
Cyber Security – Security Management Controls |
January 1, 2018
|
|
From January 1, 2018 to August 10, 2018, the sections 2 and 3 of attachment 1 of the CIP-003-6 standard for low impact BES Cyber Systems were implemented at different dates. In decision
D-2019-033, the Régie set to January 1, 2020 the withdrawal date for standard CIP-003-6 as well as its Quebec Appendix. |
CIP-003-7
|
Cyber Security — Security Management Controls | January 1, 2020
D-2019-033 |
October 1, 2021
D-2020-118 |
|
CIP-004-5.1
|
Cyber Security — Personnel & Training |
January 1, 2017
|
January 1, 2018
|
|
CIP-005-5
|
Cyber Security — Electronic Security Perimeter(s) |
January 1, 2017
|
October 1, 2022
|
|
CIP-005-6
|
Cyber Security — Electronic Security Perimeter(s)
|
October 1, 2022
D-2020-118 |
October 1, 2023
D-2022-021 |
|
CIP-006-5
|
Cyber Security — Physical Security of BES Cyber Systems | January 1, 2017
D-2016-119 D-2016-138 D-2017-031 |
January 1, 2018
D-2017-117 |
|
CIP-007-5
|
Cyber Security — System Security Management | January 1, 2017
D-2016-119 D-2016-138 D-2017-031 |
January 1, 2018
D-2017-117 |
|
CIP-008-5
|
Cyber Security — Incident Reporting and Response Planning |
January 1, 2017
|
October 1, 2022
|
|
CIP-009-5
|
Cyber Security — Recovery Plans for BES Cyber Systems | January 1, 2017
D-2016-119 D-2016-138 D-2017-031 |
January 1, 2018
D-2017-117 |
|
CIP-010-1
|
Cyber Security — Configuration Change Management and Vulnerability Assessments | January 1, 2017
D-2016-119 D-2016-138 D-2017-031 |
January 1, 2018
D-2017-117 |
|
CIP-010-2
|
Cyber Security — Configuration Change Management and Vulnerability Assessments |
January 1, 2018
|
October 1, 2022
|
|
CIP-010-3
|
Cyber Security — Configuration Change Management and Vulnerability Assessments | October 1, 2022
D-2020-118 |
October 1, 2023
D-2022-021 |
|
CIP-011-1
|
Cyber Security — Information Protection | January 1, 2017
D-2016-119 D-2016-138 D-2017-031 |
January 1, 2018
D-2017-117 |
|
CIP-013-1
|
Cyber Security - Supply Chain Risk Management
|
October 1, 2022
D-2020-118 |
October 1, 2023
D-2022-021 |
|
CIP-014-2
|
Physical Security | July 1, 2018
D-2017-117 |
April 1, 2023
D-2022-133 |
|
COM-001-1.1
|
Telecommunications | April 1, 2015
D-2014-216 |
April 1, 2017
D-2016-195 |
From April 1, 2015 to April 1, 2017 all requirements of COM-001-1.1 standard were in effect. |
COM-001-1.1
|
Telecommunications | April 1, 2017
D-2016-195 |
January 1, 2018
|
From April 1, 2017 to January 1, 2018 only requirement R4 of COM-001-1.1 standard was in effect. |
COM-001-2.1
|
Communications |
April 1, 2017
|
April 1, 2021
|
|
COM-002-2
|
Communication and coordination | January 1, 2016
D-2015-168 |
January 1, 2018
D-2016-195 |
|
EOP-001-2.1b
|
Emergency Operations Planning | April 1, 2015
D-2014-216 |
April 2, 2017
D-2017-015 |
|
EOP-002-3.1
|
Capacity and Energy Emergencies | January 1, 2016
D-2015-168 |
April 2, 2017
D-2017-015 |
|
EOP-003-2
|
Load Shedding Plans | January 1, 2017
D-2016-150 |
April 2, 2017
D-2017-015 |
|
EOP-004-2
|
Event Reporting |
January 1, 2018
|
January 1, 2021
|
|
EOP-005-2
|
System Restoration from Blackstart Resources |
April 1, 2016
|
January 1, 2021
|
|
EOP-006-2
|
System Restoration Coordination |
April 1, 2016
|
January 1, 2021
|
|
EOP-008-1
|
Loss of Control Center Functionality |
April 1, 2016
|
January 1, 2021
|
|
EOP-011-1
|
Emergency Operations
|
April 2, 2017
|
October 1, 2024
|
|
FAC-001-2
|
Facility Interconnection Requirements |
January 1, 2018
|
July 1, 2021
|
|
FAC-001-3
|
Facility Interconnection Requirements |
July 1, 2021
|
April 1, 2022
|
Editorial changes. |
FAC-001-3
|
Facility Interconnection Requirements
|
April 1, 2022
|
October 1, 2024
|
|
FAC-002-2
|
Facility Interconnection Studies |
January 1, 2018
|
October 1, 2022
|
|
FAC-002-3
|
Facility Interconnection Studies
|
October 1, 2022
|
October 1, 2024
|
|
FAC-003-3
|
Transmission Vegetation Management |
R3 – July 1, 2017
|
April 1, 2021
D-2020-067 |
|
FAC-008-3
|
Facility Ratings |
July 1, 2017
|
April 1, 2022
|
|
FAC-010-2.1
|
System Operating Limits Methodology for the Planning Horizon |
January 1, 2016
|
April 1, 2019
|
|
FAC-010-2.1
|
System Operating Limits Methodology for the Planning Horizon | April 1, 2019
D-2018-101 D-2019-032 D-2019-162 D-2020-156 |
October 1, 2021
D-2021-078 |
|
FAC-011-2
|
System Operating Limits Methodology for the Operations Horizon |
January 1, 2016
|
April 1, 2019
|
|
FAC-011-2
|
System Operating Limits Methodology for the Operations Horizon | April 1, 2019
D-2018-101 D-2019-032 D-2019-162 D-2020-156 |
October 1, 2021
D-2021-078 |
|
INT-004-3
|
Dynamic Transfers |
October 1, 2017
|
April 1, 2018
|
|
INT-004-3.1
|
Dynamic Transfers |
April 1, 2018
|
July 1, 2021
|
|
INT-006-4
|
Evaluation of Interchange Transactions | April 1, 2017
D-2017-012 |
October 1, 2021
D-2021-058 |
|
INT-009-2
|
Implementation of Interchange |
April 1, 2017
|
April 1, 2018
D-2018-017 |
|
INT-009-2.1
|
Implementation of Interchange | April 1, 2018
D-2018-017 |
October 1, 2021
D-2021-058 |
|
INT-010-2
|
Interchange Initiation and Modification for Reliability | April 1, 2017
D-2017-012 |
April 1, 2018 D-2018-017 |
|
INT-010-2.1
|
Interchange Initiation and Modification for Reliability | April 1, 2018
D-2018-017 |
July 1, 2021
D-2021-058 |
|
IRO-001-1.1
|
Reliability Coordination - Responsabilities and Authorities | April 1, 2016
D-2016-011 |
July 1, 2017
D-2017-061 |
|
IRO-002-2
|
Reliability Coordination – Facilities | January 1, 2016
D-2015-168 |
July 1, 2017
D-2017-061 |
|
IRO-002-4
|
Reliability Coordination – Monitoring and Analysis |
April 1, 2022
|
April 1, 2022
|
The standard IRO-002-4 and its Québec Appendix, in their French and English versions, as adopted per decision D-2021-047, have never come into force. |
IRO-002-4
|
Reliability Coordination - Monitoring and Analysis |
July 1, 2017
|
August 1, 2022
|
|
IRO-003-2
|
Reliability Coordination – Wide-Area View | January 1, 2016
D-2015-168 |
July 1, 2017
D-2017-061 |
|
IRO-004-2
|
Reliability Coordination – Operations Planning | January 1, 2016
D-2015-168 |
July 1, 2017
D-2017-061 |
|
IRO-005-3.1a
|
Reliability Coordination - Current Day Operations | April 1, 2016
D-2016-034 |
July 1, 2017 - R1 to R10 & R12
D-2017-061 |
Except requirement R11, all other requirements of this standard are withdrawn on July 1, 2017. |
IRO-005-3.1a
|
Reliability Coordination - Current Day Operations
|
April 1, 2016
D-2016-034 |
July 1, 2024 – R11
|
The last in effect requirement of this standard is withdrawn on July 1, 2024.
|
IRO-008-1
|
Reliability Coordinator Operational Analyses and Real-time Assessments
|
January 1, 2017
D-2016-150 |
July 1, 2017
D-2017-061 |
|
IRO-009-1
|
Reliability Coordinator Actions to Operate Within IROLs
|
January 1, 2017
D-2016-150 |
July 1, 2017
D-2017-061 |
|
IRO-010-1a
|
Reliability Coordinator Data Specification and Collection
|
January 1, 2017
D-2016-150 |
July 1, 2017
D-2017-061 |
|
IRO-010-2
|
Reliability Coordinator Data Specification and Collection |
July 1, 2017
|
August 1, 2022
|
|
IRO-010-2
|
Reliability Coordinator Data Specification and Collection |
April 1, 2022
|
October 1, 2022
|
|
IRO-010-3
|
Reliability Coordinator Data Specification and Collection
|
October 1, 2022
|
October 1, 2024
|
|
IRO-014-1
|
Procedures, Processes, or Plans to Support Coordination Between Reliability Coordinators | April 1, 2015
D-2014-216 |
July 1, 2017
D-2017-061 |
|
IRO-015-1
|
Notifications and Information Exchange Between Reliability Coordinators | April 1, 2015
D-2014-216 |
July 1, 2017
D-2017-061 |
|
IRO-016-1
|
Coordination of Real-time Activities Between Reliability Coordinators | April 1, 2015
D-2014-216 |
January 1, 2017
D-2016-150 |
From April 1, 2015 to January 1, 2017 all requirements of IRO-016-1 standard were in effect. |
IRO-016-1
|
Coordination of Real-time Activities Between Reliability Coordinators | January 1, 2017
D-2016-150 |
July 1, 2017
D-2017-061 |
From January 1, 2017 to July 1, 2017 only requirement R1 of IRO-016-1 standard was in effect. |
MOD-016-1.1
|
Documentation of Data Reporting Requirements for Actual and Forecast Demands, Net Energy for Load, and Controllable Demand-Side Management |
January 1, 2016
|
April 1, 2020
|
|
MOD-017-0.1
|
Aggregated Actual and Forecast Demands and Net Energy for Load |
July 1, 2016
|
April 1, 2020
D-2019-178 |
|
MOD-018-0
|
Treatment of Nonmember Demand Data and How Uncertainties are Addressed in the Forecasts of Demand and Net Energy for Load | July 1, 2016
D-2016-066 |
April 1, 2020
D-2019-178 |
|
MOD-019-0.1
|
Reporting of Interruptible Demands and Direct Control Load Management | July 1, 2016
D-2016-066 |
April 1, 2020
D-2019-178 |
|
MOD-020-0
|
Providing Interruptible Demands and Direct Control Load Management Data to System Operators and Reliability Coordinators |
January 1, 2016
|
July 1, 2021
D-2021-058 |
|
MOD-021-1
|
Documentation of the Accounting Methodology for the Effects of Demand Side Management in Demand and Energy Forecasts | July 1, 2016
D-2016-066 |
April 1, 2020
D-2019-178 |
|
MOD-031-2
|
Demand and Energy Data |
April 1, 2020 for functions other than DP
|
October 1, 2022
|
|
MOD-033-1
|
Steady-State and Dynamic System Model Validation |
January 1, 2019
|
October 1, 2022
|
|
PER-001-0.2
|
Operating Personnel Responsibility and Authority | April 1, 2015
D-2014-216 |
July 1, 2017
D-2017-061 |
|
PER-003-1
|
Operating Personnel Credentials Standard |
April 1, 2016
|
July 1, 2021
|
|
PER-004-2
|
Reliability Coordination — Staffing |
April 1, 2017
|
January 1, 2022
|
|
PRC-001-1
|
System Protection Coordination |
January 1, 2016
|
January 1, 2021
|
|
PRC-001-1.1(ii)
|
System Protection Coordination
|
January 1, 2021
D-2020-131 |
July 1, 2023
D-2021-070 D-2021-070R |
Withdrawal of requirements R1, R2, R5 and R6.
|
PRC-001-1.1(ii)
|
System Protection Coordination
|
July 1, 2023
|
October 1, 2024
|
Withdrawal of requirements R3 and R4
|
PRC-004-5(i)
|
Protection System Misoperation Identification and Correction |
April 2, 2017
|
April 1, 2021
D-2020-167 |
Consult the Quebec Appendix of the standard. |
PRC-004-5(i)
|
Protection System Misoperation Identification and Correction | April 1, 2021
D-2020-167 |
October 1, 2021
D-2021-058 |
|
PRC-005-2
|
Protection System Maintenance |
January 1, 2017
|
April 1, 2021
|
|
PRC-006-3
|
Automatic Underfrequency Load Shedding |
October 1, 2018
|
October 1, 2022
|
|
PRC-019-1
|
Coordination of Generating Unit or Plant Capabilities, Voltage Regulating Controls, and Protection |
January 1, 2017
|
January 1, 2021
|
|
PRC-021-1
|
Under-Voltage Load Shedding Program Data | July 1, 2016
D-2016-066 |
April 2, 2017
D-2017-015 |
|
PRC-023-3
|
Transmission Relay Loadability |
January 1, 2018
|
January 1, 2021
D-2020-131 |
|
PRC-024-1
|
Generator Frequency and Voltage Protective Relay Settings | D-2018-118 | April 1, 2021
D-2020-167 |
Since the review process is still ongoing, although adjourned (see letter of October 30, 2018 – only available in French), this standard remains in effect until April 1, 2021, or until a final decision is rendered in file R-4015-2017. The text of the standard is available here. |
PRC-025-1
|
Generator Relay Loadability |
October 1, 2017
|
October 1, 2022
|
|
TOP-001-1a
|
Reliability Responsibilities and Authorities | January 1, 2016
D-2015-168 |
July 1, 2017
D-2017-061 |
|
TOP-001-3
|
Transmission Operations |
July 1, 2017
|
August 1, 2022
|
|
TOP-001-3
|
Transmission Operations |
April 1, 2022
D-2021-047 |
July 1, 2023
D-2022-031 |
The enforcement date of the standard TOP-001-3, as adopted per decision D-2021-047, was August 1, 2022.
|
TOP-002-2.1b
|
Normal Operations Planning | July 1, 2016
D-2016-059 |
July 1, 2017 - R1 to R11 & R13 to R19
D-2017-061 |
Except requirement R12, all other requirements of this standard are withdrawn on July 1, 2017. |
TOP-002-2.1b
|
Normal Operations Planning
|
July 1, 2016
D-2016-059 |
July 1, 2024 – R12
|
The last in effect requirement of this standard is withdrawn on July 1, 2024.
|
TOP-003-1
|
Planned Outage Coordination | January 1, 2016
D-2015-168 |
July 1, 2017
D-2017-061 |
|
TOP-003-3
|
Operational Reliability Data |
July 1, 2017
|
August 1, 2022
|
|
TOP-003-3
|
Operational Reliability Data |
April 1, 2022
|
October 1, 2022
|
|
TOP-003-4
|
Operational Reliability Data
|
October 1, 2022
|
October 1, 2024
|
|
TOP-004-2
|
Transmission Operations | April 1, 2015
D-2014-216 |
July 1, 2017
D-2017-061 |
|
TOP-005-2a
|
Operational Reliability Information | April 1, 2016
D-2016-011 |
July 1, 2017
D-2017-061 |
|
TOP-006-2
|
Monitoring System Conditions | July 1, 2016
D-2016-059 |
July 1, 2017
D-2017-061 |
|
TOP-007-0
|
Reporting System Operating Limit (SOL) and Interconnection Reliability Operating Limit (IROL) Violations | April 1, 2015
D-2014-216 |
July 1, 2017
D-2017-061 |
|
TOP-008-1
|
Response to Transmission Limit Violation | April 1, 2015
D-2014-216 |
July 1, 2017
D-2017-061 |
|
TPL-007-3
|
Transmission System Planned Performance for Geomagnetic Disturbance Events | April 1, 2021
D-2021-015 |
April 1, 2023
D-2022-110 |
|
VAR-001-4.1
|
Voltage and Reactive Control | January 1, 2017
D-2016-150 |
April 1, 2018 D-2018-017 |
|
VAR-002-3
|
Generator Operation for Maintaining Network Voltage Schedules |
January 1, 2017
|
January 1, 2021
D-2020-131 |
© Gouvernement du Québec, 2024